UPGRADE OF TALNAKH CONCENTRATOR
(TOF): STAGE 3
Project summary
Major capacity expansion based on proven technology to process growing Talnakh ore volume and to unlock strategic optionality of the South Cluster development project.
Project status
- Ore dressing and ore feeders: the metal frame is 75% complete, installation of fences and preparations to install the process equipment are in progress
- Installation of reinforced concrete and metal structures is in progress
- Deliveries of core process equipment are underway
- Power supply facilities are under construction
- The water recycling system is under construction
- The bulk of works to install the process equipment is planned for completion in 2023
Projected implementation timelineSubject to import substitution of flotation equipment and the target delivery schedule being met.
Commissioning before the end of 2024 and ramp-up to design capacity in 2025.